Concrete Execution

Concrete Execution

STEP 1: SITE PREPARATION & PLANNING
  • Sub grade must be compacted and free of standing water
  • Forms must be secure and capable of withstanding load pressure of fresh concrete
  • Arrange enough help to place and finish concrete. Start with a minimum of two (2) people for a 2 cubic yard pour. Add one (1) person for each additional cubic yard of concrete. If you are using wheelbarrows to move the concrete from the truck to the forms, add an additional person.
  • Assign specific responsibilities to helpers before concrete arrives (I.e. who screeds, bull floats, washes tools, etc.)
  • Provide acceptable access for delivery:
    • Pathway must be of stable soil (support of up to 80,000 pounds)
    • Pathway must be at least ten (10) feet wide and fourteen (14) feet high
    • Avoid bringing trucks over curbs, sidewalks, or driveways.
  • The discharge chutes can reach approximately twelve (12) feet
  • Determine what type of control joints will be used to control cracking; hand tooled or saw cut TIPS:
    • Concrete used for residential applications should be at least four (4) inches thick
    • Placement of control joints should be determined in the planning step
    • Control joints should be placed no more than ten (10) feet apart
    • Sections should be square or nearly so 
    • The joint depth should be at least ¼ the thickness of the concrete
    • Avoid creating triangles or odd shaped panels when placing joints
STEP 2: PLACEMENT
  • Concrete must be discharged as close to final position as possible (eliminate "dragging" concrete long distances)
  • Concrete must be discharged in a timely manner upon arriving to the job site. If you are using wheelbarrows to move the concrete from the truck to the forms, make sure you have enough help to finish the project in a timely manner.
  • During the placement process, follow these easy steps:
    • Strike off or "screed" the concrete to the proper elevation or form height with a wood or magnesium straight edge
    • Immediately after striking off and before bleed water appears, the concrete must be bull floated and the edges formed with an edger.
    • After bull floating, no finishing practices must take place until bleed water has completely evaporated.
  • Concrete will be glossy when bleed water is present and will dull when it evaporates.
STEP 3: FINISHING

Finishing is the process of texturing the concrete. If you are using hand-tooled control joints, these must be completed prior to final texturing. The following textures may be applied:

  • A broom or brush finish is recommended for exterior applications that require maximum skid resistance such as; sidewalks and driveways. To achieve a broom finish; simply push or pull a street broom across the concrete when it reaches a good stiff consistency; timing is a judgment call based on desired depth of broom texture.
  • A porous trowel finish is recommended for exterior applications that require minimal skid resistance such as; patios and porches. To achieve a porous trowel finish; trowel the concrete when it reaches a consistency that supports your weight but leaves footprints approximately ¼" deep.
  • A hard trowel finish is recommended for interior applications that require a non-porous surface such as shop floors and garage floors. To achieve a hard trowel finish the concrete must be finished with a power trowel.
  • For decorative or architectural finishes we recommend that you hire a qualified concrete contractor that specialize in decorative concrete.
STEP 4: CURING

Curing is the most important step in concrete placement, yet is typically the most neglected. To ensure that concrete reaches its maximum designed strength and durability, it must be properly cured. This process must begin as soon as the concrete will accept the process without damage to the surface. There are two methods for curing concrete:

  • Wet Curing is the process of keeping the concrete surface saturated. A garden sprinkler is typically used for this type of curing.
  • Curing Compound is a chemical that seals in the moisture. This is typically applied with a sprayer but can also be rolled on with a paint roller.

Useful items:
Online Concrete Estimator
More on casting larger floors here

Edit

 

Construction Review in Israel<< Why do I need Quality Assurance >>Construction Review in Israel<< Concrete Execution >>Construction Review in Israel<< Concrete Terms Glossary  >>Construction Review in Israel<< Construction Terms Glossary >>Construction Review in Israel<< TRADES: Functions and terms >>Construction Review in Israel<< RAL Color Chart >>Construction Review in Israel<< RAL Color Chart 2 >>Construction Review in Israel 

Send mail to our with questions or comments about this web site.
Copyright January.1.2007, Last modified: April 28, 2015
Today's date: Wednesday, January 17, 2018   Inspection Products Site Map
Cookie Usage